Execution Timeline
12 components across all rooms
| Component | Location | Status | Progress | Planned Start | Planned End | Vendor |
|---|---|---|---|---|---|---|
| Italian Marble FlooringFLOORING | Ground Floor → Living Room | Active | 62% | 1 Aug 2025 | 15 Sept 2025 | ABC Marble |
| Wall PanellingWALL | Ground Floor → Living Room | Active | 45% | 15 Aug 2025 | 15 Oct 2025 | WoodCraft Co. |
| Chandelier FixtureLIGHTING | Ground Floor → Dining Room | Active | 70% | 1 Sept 2025 | 1 Oct 2025 | LightingHub |
| Modular KitchenKITCHEN | Ground Floor → Kitchen | Active | 25% | 1 Sept 2025 | 15 Nov 2025 | WoodCraft Co. |
| Teak Veneer WardrobesCARPENTRY | First Floor → Master Bedroom | Active | 40% | 15 Aug 2025 | 30 Oct 2025 | WoodCraft Co. |
| Brass FixturesBATHROOM_FIXTURE | First Floor → Bathroom 2 | Active | 50% | 1 Sept 2025 | 20 Sept 2025 | LuxFittings |
| Kitchen BacksplashWALL | Ground Floor → Kitchen | Issue | 80% | 15 Sept 2025 | 10 Oct 2025 | FloorCraft |
| Recessed LightingLIGHTING | Ground Floor → Living Room | Pending | 0% | 1 Oct 2025 | 15 Nov 2025 | LightingHub |
| Premium Interior PaintPAINT | Ground Floor → Living Room | Pending | 0% | 1 Nov 2025 | 15 Dec 2025 | PaintPro |
| Porcelain Floor TilesFLOORING | Ground Floor → Dining Room | Done | 100% | 1 Jul 2025 | 20 Jul 2025 | FloorCraft |
| Hardwood FlooringFLOORING | First Floor → Master Bedroom | Done | 100% | 15 Jul 2025 | 5 Aug 2025 | FloorCraft |
| Floor & Wall TilesFLOORING | First Floor → Bathroom 2 | Done | 100% | 1 Jul 2025 | 25 Jul 2025 | FloorCraft |